Pennsylvania has more than 100 proposed data center projects, but only a few large campuses have started work. In western Pennsylvania, Aligned Data Centers broke ground on Project Phoenix in Beaver County on September 10, 2026, and the Homer City redevelopment in Indiana County began construction this year. For contractors, the labor question goes well beyond electricians: abatement and demolition crews, scaffold carpenters, mechanical insulators, fireproofers and coatings applicators are all needed on these campuses.
Last reviewed: November 9, 2026. Cruitfly is following the projects below. It is not working on them. "Not announced" means the information is not public yet. We will update this page as general contractors, tenants and schedules are named.
The Pennsylvania Department of Environmental Protection runs a public data center permit tracker, which showed at least 100 proposed projects when it launched in August 2026. Most have not formally started state permitting, and a consultant on the Springdale project told TribLive there is "more speculation than reality". These are the projects with enough public detail for a contractor to plan around:
| Project | Location | Developer or user | Contractor named | Status | Timing |
|---|---|---|---|---|---|
| Project Phoenix | Shippingport Industrial Park, Beaver County | Aligned Data Centers | Holder Construction and Kokosing | Broke ground September 10, 2026 | Not announced |
| Homer City campus | Center and Blacklick townships, Indiana County | Homer City Redevelopment; Amazon filed a data center campus plan | Kiewit on the gas plant; data center contractor not announced | Construction began in 2026; the county accepted Amazon's plan for review on October 14, which is not an approval | Amazon's filing showed a December start and phases to 2036; the county has 90 days to decide |
| Misty Hollow | Forward Township, Butler County | 614 Prospect Road LLC, with GridSwitch Asset Management Services | Not announced | Revised plans in township review; next meeting November 24, 2026 | Estimated fall 2027 start |
| Springdale data center | Former Cheswick Generating Station, Allegheny County | Dynamo DC | Not announced | Council approved a conditional use; further approvals needed | Not announced |
| Keystone Connect | Former Alcoa Technical Center, Upper Burrell, Westmoreland County | TECfusions | Not announced | Further approvals needed | Not announced |
| Big Beaver | Big Beaver Borough, Beaver County | Switch | Not announced | Plans filed with the borough | First phase as early as January 2028 |
| Highridge Business Park | Schuylkill County | Nebius | Not announced | Plans detailed in July 2026; about 600 acres, six buildings in site plans | First phase expected to be operational by October 2027 |
| Salem and Falls campuses | Luzerne and Bucks counties | Amazon | Not announced | Announced June 2025; we could not confirm 2026 construction status | Not announced |
Two large sites in the region have started work. Project Phoenix is a planned 2-gigawatt, three-facility campus next to the old Bruce Mansfield coal plant, with about 3,000 construction jobs expected. The Homer City redevelopment is replacing a former coal plant with a gas plant of about 4.5 gigawatts, and Amazon has filed plans for the data center campus around it.
Springdale, Upper Burrell, Forward Township and Big Beaver are still in approvals. Misty Hollow has its own project page.
Based on what developers have filed or said publicly:
Treat every date as an estimate. Under Executive Order 2026-05, signed August 18, 2026, local land-use approval comes before state permits for projects over 25 megawatts, and data centers no longer use the state's fast track permit program. A project can be well known and still be a long way from breaking ground.
Yes, and data centers are adding to a gap that already existed. ABC Eastern Pennsylvania says data center demand "intensifies an existing workforce gap", pulling on the same people needed for hospitals, higher education and industrial work. The Associated Press reported that Boilermakers Local 154 in southwestern Pennsylvania went from recruiting no apprentices for four years to assembling a class of more than 200, and still needs more.
Overlap is the risk for contractors. Project Phoenix and Homer City are already moving, and more campuses could follow within the same few years, so experienced crews may be committed before a later project needs them.
The trades follow the site. Many of the Pennsylvania projects above are on former power plant or industrial land, which changes what comes first:
The full phase-by-phase list is on our data center construction staffing page.
Cruitfly staffs the specialty trades around the electrical work, and it does not supply electricians. Every worker is a W2 Cruitfly employee covered by Cruitfly's workers' compensation, certified payroll is produced weekly, and typical fill time is 48 to 72 hours. Every asbestos worker Cruitfly places holds a current license issued by the state where the project is located. Most Cruitfly workers carry OSHA 10, especially when the client requires it. See the compliance page and Pennsylvania staffing.
Recent work that maps to a campus: 86 demolition and abatement workers on a Georgia university project, 30 scaffold carpenters and helpers for a Wyoming power plant shutdown, and a mechanical insulation crew scaled from three to six in two weeks. For electricians and other trades, see the best data center construction staffing agencies.
Bidding on a Pennsylvania data center package? Request workers from Cruitfly or call 317-426-7703.
Project Phoenix in Shippingport, Beaver County, broke ground on September 10, 2026, and the Homer City redevelopment in Indiana County began construction in 2026. Springdale, Upper Burrell, Forward Township and Big Beaver are still in approvals.
The state's permit tracker showed at least 100 proposed projects when it launched in August 2026, and most had not formally started state permitting.
Yes. ABC Eastern Pennsylvania says data center demand intensifies an existing workforce gap, and the Associated Press reported one southwestern Pennsylvania Boilermakers local building an apprentice class of more than 200 after four years without recruiting.
Asbestos abatement and demolition crews, scaffold carpenters, mechanical insulators, fireproofers, coatings applicators and, once on-site power plants run, shutdown crews.
No. Cruitfly staffs the specialty trades around the electrical work. Every worker is a W2 Cruitfly employee, and typical fill time is 48 to 72 hours.
Need a certified crew on site? Tell us the project, the start date and the certifications you need. Typical fill is 48 to 72 hours, and every worker is a W2 Cruitfly employee covered by our workers' compensation. Prefer to talk? Call 317-426-7703.